Network Rail => S&C Replacement Project

Come up with a process and method to replace Switch & Crossings (S&C) in existing track, given the following: 1) maximum time is 8 hours; 2) Handback of the S&C at linespeed; 3) MTBF for the whole system 3.5 years; 4) costsavings of 28%.

The end result: using System Engineering, all technical and operational issues were solved; cost savings theoretically achieved of 24%.

At this moment of time phase 1 to 3 (of the 5 phases) is implemented.